No positions in the markets we measure BY 07:30 ET
CCIR Compute Credit
Index Research
Credit · Tracked as filed as of 2026-07-02

Crusoe

CCIR tracks 10 instruments issued by Crusoe: credit facility. Every row traces to a primary document. Sizes are as filed and are not additive across the capital stack.

Capital stack by borrower

Which entity owes what, as filed. Facilities raised in a subsidiary sit on that subsidiary's assets; the parent's own paper sits beside them, senior to nothing below it.

BorrowerInstrumentSize $mRate
Crusoe (parent level) Goldman Sachs loan, AMD backstop 300 6%
Victory Park Capital facility 175 Undisclosed
Brookfield credit facility 750 Undisclosed
Upper90-led syndicated credit facility 225 Undisclosed
SVB Capital / Sparkfund / Generate credit facilities 155 Undisclosed
Upper90 project financing 40 Undisclosed
Upper90 initial equipment loan Undisclosed
Blue Owl / Crusoe / Primary Digital Abilene JV Abilene Phase 2 construction loan 7,100 Undisclosed
Abilene Phase 1 construction loan 2,300 Undisclosed
Crusoe Technologies LLC First GPU debt facility 200 Undisclosed

Instruments

Goldman Sachs loan, AMD backstop

Credit facility $300m 6% Reported 2026-02-19/20
Seniority
Secured (AMD chips + equipment)
Maturity
Undisclosed
Collateral
AMD chips + equipment; AMD commits to lease back chips if customers lapse (vendor credit-enhancement backstop); Ohio DC built by 5C
Lenders
Goldman Sachs (arranger) · AMD (credit enhancement)
Pricing
~6% press-reported; tenor undisclosed. Close unconfirmed — no company/lender release
Terms
~$300M press-reported

Source: The Information; Reuters pickup · document

Victory Park Capital facility

Credit facility $175m Undisclosed Entered 2025-08-25
Seniority
Asset-backed in character
Maturity
Undisclosed
Collateral
Funds GB200 NVL72 at atNorth ICE02, Iceland
Lenders
Victory Park Capital (Janus Henderson affiliate)

Source: Crusoe newsroom · document

Brookfield credit facility

Credit facility $750m Undisclosed Entered 2025-06-11
Seniority
Corporate-level growth capital
Maturity
Undisclosed
Collateral
Collateral unspecified ("AI factories")
Lenders
Brookfield Asset Management (Infrastructure Debt); Eastdil advised

Source: Crusoe newsroom · document

Abilene Phase 2 construction loan

Credit facility $7,100m Undisclosed Entered 2025-05-22
Borrower
Blue Owl / Crusoe / Primary Digital Abilene JV (borrower — not Crusoe corporate)
Seniority
Project-level
Maturity
Undisclosed
Collateral
6 more buildings → 1.2 GW campus
Lenders
J.P. Morgan-led consortium (others unnamed); Newmark arranged
Terms
Within $11.6B debt+equity phase-2 package; $15B JV

Source: Newmark release · document

Upper90-led syndicated credit facility

Credit facility $225m Undisclosed Entered 2025-03-27
Seniority
GPU-backed
Maturity
Undisclosed
Collateral
GPU-backed — proceeds exclusively for NVIDIA GPUs + cloud infrastructure
Lenders
Upper90 (lead) · BCI · FS Investments · King Street · Liberty Mutual Investments · ORIX USA

Source: Upper90 release + Crusoe newsroom · document

Abilene Phase 1 construction loan

Credit facility $2,300m Undisclosed Entered 2025-01-22
Borrower
Blue Owl / Crusoe / Primary Digital Abilene JV (borrower — not Crusoe corporate)
Seniority
Project-level construction loan
Maturity
Undisclosed
Collateral
206 MW build-to-suit leased to Oracle (Stargate flagship)
Lenders
J.P. Morgan; Newmark arranged

Source: Newmark release · document

First GPU debt facility

Credit facility $200m Undisclosed Entered 2023-10-23
Borrower
Crusoe Technologies LLC (borrower)
Seniority
GPU asset-backed
Maturity
Undisclosed
Collateral
GPU asset-backed
Lenders
Upper90 (lead)

Source: Crusoe newsroom · document

SVB Capital / Sparkfund / Generate credit facilities

Credit facility $155m Undisclosed Entered 2022-04-21
Seniority
Equipment/project-level
Maturity
Undisclosed
Collateral
Energy systems
Lenders
SVB Capital · Sparkfund · Generate Capital
Terms
Up to $155M (expandable)

Source: Crusoe newsroom · document

Upper90 project financing

Credit facility $40m Undisclosed Entered 2021-04
Seniority
Project-level, non-dilutive
Maturity
Undisclosed
Collateral
Flare-mitigation systems
Lenders
Upper90

Source: Crusoe newsroom (Series B) · document

Upper90 initial equipment loan

Credit facility Undisclosed Entered 2019
Seniority
Equipment-secured
Maturity
Undisclosed
Collateral
Equipment (flare-gas era)
Lenders
Upper90
Terms
Undisclosed

Source: Upper90 release (disclosed 2025) · document

Collateral classes on this page: out, gpu, secured_undisclosed, landlord_spv. The full ledger, with every issuer and the derived credit series, is on Compute Credit.